Construction Update: May 6, 2024

This week, underground duct bank construction will continue at the following locations in Beverly:

  • -Broadway
    • –Between 11-23 Broadway

  • -Thorndike Street
    • –Between Endicott Street and Cabot Street

  • -Hale Street
    • –Between Ocean Street and Dane Street
    • –Between Lothrop Street and the installed manhole

  • -East Lothrop Street
    • –Between East Street and Parsons Drive
    • –Between Parramatta Road and Cross Lane
    • –Between Hale Street and Bisson Street
    • –Between Bisson Street and Lawrence Street, performing pre-drilling of rock ledge

  • -Cross Lane
    • –Between Birch Woods Drive and Boyles Street

  • -Within National Grid’s property on River Street

  • -Within National Grid’s property on Boyles Street

Work hours in Beverly are from 7:00AM to 4:30PM Monday through Friday.  Please let us know about any upcoming deliveries or special events that we can prepare to assist you with.

Starting the week of May 13, crews will carry out utilities work on Bridge Street, between Pierce Avenue and the Essex Bridge, and on Waite Street in Salem. During this work, the left turn from the Essex Bridge southbound onto Bridge Street will be closed from 9:00 AM to 5:00 PM Monday through Friday. As with previous work in this area, signage will indicate that nearby businesses are open.

Please note that parking may be limited and/or through-traffic may be detoured on the following streets: Cross Lane, Hale, Thorndike, East Lothrop, and Broadway. Residents will always be able to access their homes and driveways with assistance from police details, crew members, and traffic signage.

At times construction equipment generates noise that will be noticeable to abutters. We thank you for your patience and understanding as we perform these critical infrastructure upgrades.

If you have questions, please feel free to contact a member of our project outreach team by emailing us at info@BeverlyRegionalTransmissionReliabilityProject.com, or by calling our project hotline 1-833-238-4743.

Sincerely,

The Beverly Regional Transmission Reliability Project Outreach Team

*Please note, due to the complexities of underground construction, schedule is subject to change