Next week, duct bank construction will continue at the following locations in Beverly:
- -Congress Street
- —Near the Essex Bridge
- -Wellman Street
- —At the intersection with Webber Avenue
- -East Lothrop Street
- —Between Bisson Street and East Street
- -Cross Lane
- —Between Cross Street and Spruce Run
- -Boyles Street
- —Between Cross Lane and Cole Street
Crews are installing sections of transmission line cable in completed sections of duct bank. This work involves equipment located at the manholes along the project route and does not require any excavation. Next week, work will continue at the following manhole locations:
- -#3 (on Congress Street near the MBTA tracks)
- —Preparatory work and cable installation
- -#6 (near 37 Broadway)
- —Post-installation work
- -#9 (near 203 Lothrop Street)
- —Preparatory work
- -#10 (near 2 Cavendish Square)
- —Preparatory work
In order to accelerate the completion of the project, with the agreement of the City of Beverly, extended work hours are in place at worksites on Cross Lane and Boyles Street. Some crews will continue duct bank excavation on Saturdays between 8:00 AM and 3:30 PM. Monday through Friday, work hours in Beverly are 7:00 AM to 5:00 PM. Please let us know about any upcoming deliveries or special events that we can prepare to assist you with.
At times, work vehicles may need to stage outside of active worksites for traffic management purposes.
Please note that parking may be limited and/or through-traffic may be detoured on the following streets in Beverly: Congress, Wellman, East Lothrop, Boyles, Cross Lane, and Broadway. Residents will always be able to access their homes and driveways with assistance from police details, crew members, and traffic signage.
At times, construction equipment generates noise that will be noticeable to abutters. We thank you for your patience and understanding as we perform these critical infrastructure upgrades.
If you have questions, please feel free to contact a member of our project outreach team by emailing us at info@BeverlyRegionalTransmissionReliabilityProject.com or by calling our project hotline at (833) 238-4743.
*Please note, due to the complexities of underground construction, schedules are subject to change.