Next week, underground duct bank construction will continue at the following locations in Beverly:

  • – Broadway
    • — Between 11-29 Broadway.
  • -Thorndike Street
    • — Between Endicott Street and Cabot Street. Crews are continuing work from Endicott Street.
  • – Hale Street.
    • — Between Ocean Avenue and Bancroft Street.
    • — Between Lothrop Street and the installed manhole.
  • – East Lothrop Street.
    • — Between Parsons Drive and Smithson Drive.
    • — Between Corning Street and Smithson Drive.
    • — Between Ray Street and Parramatta Road.
    • — Between Hale Street and Bisson Street.
  • – Cross Lane.
    • — Between Lakeshore Avenue and Spruce Run. Crews at this location will be performing pre-construction ledge drilling ahead of excavation.
  • – Congress Street.
    • — Between Wellman Street and Summit Avenue, working under the MBTA tracks.

Starting the week of March 18, crews will begin excavating duct bank on Cross Lane between Birch Woods Drive and Boyles Street. Work will begin approximately at the intersection with Birch Woods Drive and work towards Boyles Street.

Work hours in Beverly are from 7:00AM to 4:30PM Monday through Friday.  Please let us know about any upcoming deliveries or special events that we can prepare to assist you with.

Please note that parking may be limited and/or through-traffic may be detoured on the following streets: Hale, Abbott, Thorndike, East Lothrop, and Broadway. Residents will always be able to access their homes and driveways with assistance from police details, crew members, and traffic signage.

At times construction equipment generates noise that will be noticeable to abutters. We thank you for your patience and understanding as we perform these critical infrastructure upgrades.

If you have questions, please feel free to contact a member of our project outreach team by emailing us at info@BeverlyRegionalTransmissionReliabilityProject.com, or by calling our project hotline 1-833-238-4743.

*Please note, due to the complexities of underground construction, schedule is subject to change