Next week you can expect the following activities in Salem:
- Continued activity on National Grid property on the corner of Ferry Street and Waite Street as crews work on the Waite Street substation.
- Duct bank excavation and conduit installation on Bridge Street, between Pierce Avenue and Essex Bridge.
- Manhole excavation on Bridge Street, between Essex Bridge and Ames Street.
Next week you can expect the following activities in Beverly:
- Abutment work on Essex Bridge in preparation for spring 2023 bridge work. During the first half of next week, crews will work to take measurements under the bridge.
- Manhole excavation on Congress Street, between Essex Bridge and Summit Avenue. Work at this location will start in the second half of next week.
- Test pit excavation at the expected duct bank locations on Wellman Street and Webber Avenue.
- Excavation work inside the Beverly 12 substation on National Grid’s River Street property.
Please note that parking will be limited on Ferry Street, Waite Street, Peirce Avenue, and Bridge Street in Salem to allow for greater access for National Grid and its contractors.
In both Salem and Beverly, construction will take place between the hours of 7:00 am and 4:30 pm, Monday through Friday.
Our planned roll out of a new project schedule map has been pushed to next week, in light of a schedule shift. We look forward to sharing this information soon and are thank you for your patience.
Soil sampling, test pitting, and duct bank excavation all require the use of drills for removing pavement and rock. Additionally, excavators and vacuum trucks will be used for safe and efficient removal of soil. These pieces of equipment generate substantial noise that may be unpleasant to abutters. We thank you for your patience and understanding as we perform this vital work.
Test pit excavation is an important aspect of pre-construction activity, used to locate existing underground utilities that may not have been identified on plans or during past survey work. For test pitting at expected manhole locations, crews expect to take three to five days at each location, dependent on conditions. Crews working on test pitting excavation at duct bank locations will work along the route in a shorter timeframe.
As you know, our weekly newsletter remains one of the easiest ways to stay up to date with the latest project information related to construction schedules, timelines, and traffic. If you haven’t already, please feel free to encourage your neighbors, family, or friends who may be interested in having these weekly updates sent straight to their email inbox to sign up here (at the bottom of the homepage).
Construction is scheduled to minimize the impact on traffic and everyday life; your neighborhood and street will likely only be impacted by the construction for weeks—not years. That said, we understand that construction doesn’t always feel “short-term” when it’s in front of your home or business. As work begins in your area, we will continue to work to mitigate inconveniences that come up to the greatest extent feasible. Please let us know about upcoming deliveries, schedules, and events that could be impacted by work.
If you have questions about any of our current or upcoming work, please feel free to contact a member of our project outreach team by emailing us at info@BeverlyRegionalTransmissionReliabilityProject.com, or by calling our project hotline 1-833-238-4743.
*Please note, due to the complexities of outdoor construction, schedule is subject to change.