Construction Update: April 8, 2024

Next week, underground duct bank construction will continue at the following locations in Beverly:

  • – Broadway
    • — Between 9-23 Broadway
  • – Thorndike Street
    • — Between Endicott Street and Cabot Street
  • – Hale Street.
    • — Between Ocean Street and Bancroft Avenue
    • — Between Lothrop Street and the installed manhole
  • – East Lothrop Street
    • — Between Lawrence Street and Smithson Drive
    • — Between Corning Street and Smithson Drive
    • — Between Ray Street and Parramatta Road
    • — Between Hale Street and Bisson Street
    • — Between East Street and Parsons Drive, performing pre-drilling of rock ledge
  • – Cross Lane
    • — Between Lakeshore Avenue and Spruce Run. Crews at this location will be performing pre-construction ledge drilling ahead of excavation
    • — Between Birch Woods Drive and Boyles Street
  • – Within National Grid’s property on River Street

Work hours in Beverly are from 7:00AM to 4:30PM Monday through Friday.  Please let us know about any upcoming deliveries or special events that we can prepare to assist you with.

Please note that parking may be limited and/or through-traffic may be detoured on the following streets: Cross Lane, Hale, Thorndike, East Lothrop, and Broadway. Residents will always be able to access their homes and driveways with assistance from police details, crew members, and traffic signage.

At times construction equipment generates noise that will be noticeable to abutters. We thank you for your patience and understanding as we perform these critical infrastructure upgrades.

If you have questions, please feel free to contact a member of our project outreach team by emailing us at info@BeverlyRegionalTransmissionReliabilityProject.com, or by calling our project hotline 1-833-238-4743.

Sincerely,

The Beverly Regional Transmission Reliability Project Outreach Team

*Please note, due to the complexities of underground construction, schedule is subject to change