
Construction Update: May 16, 2022
This week you can expect the following activities: Continued activity on Waite Street as crews work to excavate and install conduit and duct bank. Barring
The Beverly Regional Transmission Reliability Project is the replacement of a 115-kilovolt underground electric transmission line in Salem and Beverly, Massachusetts. Beginning at the new Waite Street Substation in Salem and ending at National Grid’s East Beverly Substation, the cable supplies power to the local grid, serving nearly 50,000 electric customers in Beverly, Essex, Gloucester, Hamilton, Manchester, Rockport, and Wenham.
Originally installed in 1971, the cable is aging and in need of replacement.
This week you can expect the following activities: Continued activity on Waite Street as crews work to excavate and install conduit and duct bank. Barring
Dear Neighbor, This week you can expect the following activities: Continued activity on Waite Street as crews work to excavate and install conduit and duct
Dear Neighbor, This week you can expect the following activities: Work on Waite Street as crews continue to excavate and install conduit and duct bank.
This week you can expect the following activities: Continued work on Waite Street as crews excavate and install conduit and duct bank. Please note that
Call our toll-free hotline at (833) 238-4743, or email [email protected]